The Office of Management and Budget (OMB) issued memorandum, “Improving Acquisition Data Quality for Fiscal Years 2009 and 2010” dated October 7, 2009, and “Improving Federal Procurement Data Quality – Guidance for Annual Verification and Validation dated May 31, 2011. Agencies shall complete actions below in order to comply with OMB’s requirement ensuring FY 2011 FPDS data reflects accurate and timely contract information.
Mission: This summary addresses USDA’s agencies’ responsibilities to improve its procurement data through FPDS Verification & Validation (V&V) policies and procedures.
Agencies responsibilities: For the end of FY2011, agencies will:
USDA FPDS V&V
Process Timeline: The table below summarizes the timeline for the USDA
FPDS V&V Process.
|
USDA FPDS V&V Process Timeline |
|
|
Date |
Task |
|
September 30, 2011 |
Agencies complete fiscal year transactions and ensure accurate contract data. |
|
December 9, 2011 |
OPPM selects a randomly generated set of PIIDs for each specific agency. OPPM develops V&V Data Workbook with individual PIIDS and distributes them to the agencies’ POCs via email. |
|
January 13, 2012 |
Agencies compare the randomly selected contracts actions to the individual data fields entered into FPDS and populate their V&V Data Workbook. Agency Head of Contracting Activity Designee (HCA-D) submit FPDS accuracy certification to Dorothy Lilly, Chief of Procurement Policy Division (PPD) at Dorothy.Lilly@dm.usda.gov , and a copy email to Crandall Watson at Crandall.Watson@dm.usda.gov. |
|
January 13, 2012, |
Agencies complete FY 2011 Data Call Questions provided in Appendices 3 and 4. Agency HCADs submit answers along with FPDS accuracy certification to Dorothy Lilly with a copy by email to Crandall Watson. |
|
January 18, 2012 |
OPPM completes review of the agencies V&V spreadsheets. If the overall USDA department-wide accuracy percentage does not meet 0.95 ±5%; the specific agency that did not meet the required accuracy rate will be notified via email to the POC and HCAD. |
|
January 18, 2012 |
OPPM will randomly select another set of PIIDs for those specific agencies that did not meet the accuracy percentages. OPPM will re-distribute a second V&V Data Workbook to agency POC’s via email. |
|
January 23, 2012 |
Agencies compare the second set of randomly selected contracts actions to individual data fields entered in FPDS and populate their V&V Workbook. Agencies revalidate and HCADs submit the revised FPDS accuracy certification to Dorothy Lilly with a copy by email to Crandall Watson. |
|
January 27, 2012 |
Senior Procurement Executive (SPE) submits department-wide FPDS V&V results to OMB’s Office of Procurement Policy (OFPP). |
Appendix 1
Appendix 1 provides an example of the Agency V&V Data Workbook.
Please note: New FPDS Data Fields are highlighted in green
|
Individual
PIID Worksheet |
|||||
|
PIID |
ABCD1234 |
Systemic
Cause of Invalid Data |
|||
|
Field
# |
Field
Name |
C=Correct, I=Incorrect |
User |
System |
Other |
|
2A |
Date Signed |
I |
X |
|
|
|
2C |
Completion Date |
C |
|
|
|
|
2D |
Est. Ultimate Completion Date |
I |
X |
|
|
|
2E |
Last Date to Order |
C |
|
|
|
|
3A |
Base and All Options Value |
I |
X |
|
|
|
3B |
Base and Exercised Options Value |
I |
X |
|
|
|
3C |
Action Obligation |
I |
X |
|
|
|
4C |
Funding Agency ID |
C |
|
|
|
|
6A |
Type of Contract |
C |
|
|
|
|
6F |
Performance Based Service Acquisition |
C |
|
|
|
|
6M |
Description of Requirement |
C |
|
|
|
|
6SI |
Treasury Account Symbol Initiative |
C |
|
|
|
|
8A |
Product/Service Code |
C |
|
|
|
|
8G |
Principal NAICS Code |
C |
|
|
|
|
9A |
DUNS No. |
C |
|
|
|
|
9C |
Principal Place of Performance Code- State |
C |
|
|
|
|
9C |
Principal Place of Performance Code-
Country |
C |
|
|
|
|
9H |
Place of Manufacture |
C |
|
|
|
|
9K |
Place of Performance ZIP Code (+4) |
C |
|
|
|
|
10A |
Extent Competed |
C |
|
|
|
|
10C |
Other than Full and Open Competition |
C |
|
|
|
|
10D |
Number of Offers Received |
C |
|
|
|
|
10N |
Type of Set Aside |
C |
|
|
|
|
10R |
Statutory Exception to Fair Opportunity or
Fair Opportunity/Limited Sources |
C |
|
|
|
|
11A |
CO's Business Size Selection |
C |
|
|
|
|
11B |
Subcontract Plan |
C |
|
|
|
|
12A |
IDV Type |
C |
|
|
|
|
12B |
Award Type |
C |
|
|
|
|
Total Correct |
22 |
|
|
|
|
|
Total Incorrect |
5 |
|
|
|
|
|
Total Count |
28 |
|
|
|
|
|
Percentage Correct |
78.57% |
|
|
|
|
|
Total Errors By Cause |
5 |
0 |
0 |
||
|
Percentage of Total Number of Errors By
Cause |
100% |
0% |
0% |
||
|
Reviewer Name |
|
||||
|
Reviewer Signature |
|
||||
|
Fax to: |
|
||||
Appendix 2
Appendix 2 is for informational use only. This table represents an estimated number of contract actions that each agency can expect to review based upon FY 2009 data. The USDA V &V Distribution Chart for FY 2011 will correlate with FY2011 FPDS data.
|
FY 2009 FPDS |
Sum of Total Actions |
Percent of Total |
Base |
Pro-rated add on |
Total |
|
AMS |
1,612 |
2.28% |
20 |
3 |
23 |
|
ARS |
6,962 |
9.83% |
20 |
14 |
34 |
|
APHIS |
5,459 |
7.71% |
20 |
11 |
31 |
|
FSA Commodities ONLY |
1,670 |
2.36% |
20 |
3 |
23 |
|
FSA Non-Commodities ONLY |
1,556 |
2.20% |
20 |
3 |
23 |
|
FNS |
585 |
0.83% |
20 |
1 |
21 |
|
FSIS |
1,017 |
1.44% |
20 |
2 |
22 |
|
FS |
36,362 |
51.34% |
20 |
73 |
93 |
|
NRCS |
3,931 |
5.55% |
20 |
8 |
28 |
|
OIG |
158 |
0.22% |
20 |
0 |
20 |
|
RD |
7,563 |
10.68% |
20 |
15 |
35 |
|
POD |
3,946 |
5.57% |
20 |
8 |
28 |
|
USDA TOTAL |
70,821 |
100% |
240 |
142 |
382 |
*BASED
ON FY 2009 DATA
Appendix 3
FY 2011 FPDS Data Call Questions:
Please have your agencies review and answer these questions.
Improving Quality
of Data
Appendix 4
New Section “Improving the Use of Past Performance”
OPPM added a tab to the USDA V & V Workbook titled, “Contractor Past Performance”.
For each PIID all agencies shall determine whether a past performance evaluation was completed in the Contractor Performance System (CPS) or the Contractor Performance Assessment Reporting System (CPARS).
*Please Note for FY 2011 contracts/PIIDS your agency will mainly need to check PPIRS because USDA’s previously used CPS system has been retired. There is a possibility that some agencies began using CPARS before the end of FY 2010, so please check both systems if necessary.
For
each PIID your agency will enter one of the three following options:
(Y)- Entered and completed
(N)- Not entered
(P)- In process
Contractor
Performance Data Call Questions:
1.
For each contract/PIID marked with an N (no), in regards to entering a contractor performance
review, please state the reason why it has not yet been entered into either CPS
or CPARS and your agency milestone plans for bringing these records into CPARS.
2. Discuss any barriers or challenges that your agency faced in implementing accountability for inputting contractor performance evaluations throughout the agency, and any steps that the agency has taken, or is planning to take, in FY 2012 to improve past performance reporting.
Next Steps for Final Compliance:
Agency Focal Point’s will be responsible for providing a status update to their HCAD when all applicable contractor past performance evaluations for the contracts/PIIDS included in the FPDS V&V Plan (that were marked with a N) are completed for the year or within 6 months of December 16, 2011, whichever is sooner.